What the certificate is and what the law asks of the buyer
Section 57 of the Foreign Acquisitions and Takeovers Act 1975 lets a person who owns, or will own, land and plans to sell new dwellings built on it to foreign persons apply for a certificate. A near-new dwelling certificate, made under regulation 43A, does the same job for dwellings that a developer sold before where that earlier sale never settled. The initial fee for the near-new certificate is nil if the developer has applied for, or holds, a new dwelling certificate for the same development.
Section 45(1) of the Act is the provision that protects the buyer. A foreign person's purchase is not treated as a significant action when all of these line up:
- the buyer acquires the interest from the person named in the certificate;
- the development is the one specified in the certificate;
- that person gave the buyer a copy of the certificate before the buyer acquired the interest; and
- the certificate's conditions were met, or the buyer did not know at the time that one of them had not been.
This is different from the certificate an individual can hold for themselves, which covers one new dwelling or one vacant lot in a named state for about 12 months. That one is covered on the exemption certificates page.
Get your buyer plan
See your FIRB fee, state surcharge and the steps in order, worked out for your situation. Free, about a minute.
Which developments can get one
Treasury's Guidance Note 6 says a developer, Australian or foreign, can apply for a specified development if it:
- will have 50 or more dwellings, not counting townhouses;
- has development approval from the relevant government authority; and
- has foreign investment approval for the land, where that was needed, with its conditions being met.
The Act defines a "development" as one or more multi-storey buildings under one development approval, with at least 50 independent self-contained dwellings other than townhouses (regulation 15 sets the number at 50). Treasury adds that house and land packages are not a development for this purpose. A project that has not yet received unconditional approval to start building may not be eligible.
Large projects can be certified in stages. In Treasury's example, a 200-dwelling project in two stages gets a certificate for the first 90-dwelling stage, and the developer can apply again for stage two once its plans are ready. The wording on townhouses matters for buyers of townhouse projects, covered in buying a townhouse as a foreign buyer.
How the developer applies
The ATO's page for property developers describes the process: the developer logs in to Online services for foreign investors, goes to Lodgment, then Residential application, and chooses "New and near-new dwelling exemption" as the application type. The ATO's page was last updated in March 2025.
Treasury says each application is assessed case by case. Factors include:
- a marketing schedule showing when, where and how the development will be advertised in Australia;
- the number of dwellings, and details of each unit such as bedrooms, car spaces and expected price;
- who owns the development, including shareholders and beneficiaries;
- architectural plans and artist impressions; and
- compliance history, if the developer or a related party has held an earlier certificate and not met its conditions.
For 2026-27 the initial fee is $67,400. A reconciliation fee is then payable for each dwelling sold to a foreign person, equal to what that buyer would have paid applying individually. These are reported and paid every six months, within 30 days of the end of each period. Treasury's exemption certificate guidance says these applications are typically more complex than applications for individual transactions. Section 61 of the Act deals with the time limit for deciding certificate applications, so ask the ATO how it applies to a particular application.
Conditions that matter to buyers
| Condition on the developer | What it means for a foreign buyer |
|---|---|
| Market the dwellings for sale in Australia | The Act makes it an offence to sell to a foreign person without meeting an advertising condition written into the certificate (section 88) |
| Sell no more than 50% of the dwellings to foreign persons under the certificate | The certificate's capacity can run out before a project sells out |
| Sell no more than $3 million of dwellings to one foreign person | Prices are added together across the same development |
| Give each foreign buyer a copy of the certificate | The copy is one of the conditions in section 45(1) |
| Report sales every six months | A developer obligation, not a buyer task |
| Pay a fee for each dwelling sold | The developer is nominally liable, but developer and buyer can agree who pays, and a buyer can pay the ATO directly using the payment reference number on the certificate |
Worked example. A buyer purchases one apartment for $900,000 and a second for $1,100,000 in the same development. The total is $900,000 + $1,100,000 = $2,000,000, inside the $3 million limit. A third purchase at $1,200,000 would bring the total to $3,200,000, so that purchase needs its own approval. Its 2026-27 application fee falls in the "$2 million or less" band: $31,300. The developer's reconciliation fees on the first two would be $15,600 and $31,300, or $46,900 together.
What buyers commonly check
Because the protection in the Act turns on the certificate itself, buyers and their conveyancers commonly ask the developer for:
- a copy of the certificate before the contract is signed;
- confirmation that it names this development and this stage;
- the value limits that apply and where the buyer's running total sits against $3 million;
- who bears the reconciliation fee, and whether the contract price already includes it; and
- whether the developer is meeting the certificate's conditions.
None of the official pages reviewed for this guide describe a public search for these certificates. The route they describe is the developer's copy. Questions about a particular certificate can go to the foreign investment enquiry line on 1800 050 377 from Australia or +61 2 6216 1111 from overseas.
After settlement
A certificate removes the application, not the later obligations. The owner still registers the property within 30 days of settlement, lodges an annual vacancy fee return, and pays any state surcharges (see state surcharges). If a dwelling bought under a developer's certificate sits empty, the vacancy fee is double the fee the buyer would have paid applying individually. More on that in the vacancy fee amount guide. Current projects are listed under new homes.
Keep reading
- What are the FIRB rules for buying off the plan as a foreign buyer?
- Can a foreign buyer purchase a townhouse in Australia?
- How the FIRB fee works for new dwellings, off-the-plan homes and vacant land
- How does a FIRB condition work in a contract of sale?
- How does a FIRB application work, step by step?
- What are the FIRB rules for buying vacant land and building a home?
Frequently asked questions
Do I still need FIRB approval if the developer holds a certificate?
The ATO says no, where the developer already has an exemption certificate for the dwelling. The cover is conditional: the certificate must name the development, the developer must give a copy before you acquire the interest, and your total in the development must stay within $3 million. Above that, your own approval is needed.
Can I buy more than one home under the same certificate?
Yes, up to $3 million in total within the development. Treasury says to add the price of the current purchase to the price of everything else bought there under the same certificate. A single dwelling worth more than $3 million is outside the certificate on its own.
What if the certificate does not cover my purchase?
Your own approval or your own exemption certificate has to be in place before the purchase becomes binding. Treasury notes a contract can be signed if it is conditional on approval, and the ATO says a certificate can still be applied for while a contract remains conditional.
Does the developer's certificate remove the vacancy fee?
No. Owners who bought under a developer's certificate still lodge a vacancy fee return each year, and the fee, if it applies, is worked out as double the application fee they would have paid individually.
Who pays the fees on a certificate?
The developer pays the initial fee and the per-dwelling reconciliation fees to the ATO. Treasury says the developer and buyer can agree between themselves who bears the per-dwelling fee, so contracts and price lists are where to look.
Sources
- Guidance Note 6: Residential Land (version 5, 1 July 2026), Treasury
- Guidance Note 9: Exemption certificates, Treasury
- Guidance Note 10: Fees (version 12, 19 September 2026), Treasury
- Schedule of Fees (version 8, 1 July 2026), Treasury
- Exemption certificates for property developers, ATO
- Residential property application for foreign investors, ATO
- Foreign Acquisitions and Takeovers Act 1975, Federal Register of Legislation
- Foreign Acquisitions and Takeovers Regulation 2015, Federal Register of Legislation
Checked 5 October 2026.
firbapproval.com.au is an independent guide. It is not affiliated with, endorsed by or connected to the Foreign Investment Review Board, the Australian Treasury or the Australian Taxation Office. We do not lodge or process applications. Applications are made to the ATO. General information only, not legal, tax, migration or financial advice.